Subcontract details

Layher Allround multidirectional scaffolding

Client: Arsenal do Alfeite

Location: Almada
Execution Period: 4 months

Description:
Contract for the improvement, inspection and surface treatment of the Sagres school ship. 20 tonnes of multidirectional scaffolding were erected on the three masts and groups.

GALLERY

CLICK ON THE IMAGES TO ENLARGE

SEE OTHER PROJECTS

SALDANHA

2023-11-17T11:39:18+00:00

“SALDANHA” PROJECT

Subcontract details

Layher Blitz facade scaffolding and Layher Allround multidirectional scaffolding

Client: Sacyr Somague 

Location: Monumental Building, Saldanha
Execution Period: 12 months

Desciption:
Contract for remodelling and improving the monumental building. Approximately 10,000 square metres of scaffolding were erected with various accessories and types of scaffolding, including cantilevers, suspended scaffolding and interior back scaffolding. These scaffoldings varied in height up to a maximum of 42 metres. In total they represent 200 tonnes of “facade” scaffolding. Various access stairs, mobile towers, platforms, cinemas and lift boxes were also erected on the multidirectional scaffolding.

GALERY

CLICK ON THE IMAGES TO ENLARGE

SEE OTHER PROJECTS

ALMARJÃO

2023-11-17T11:35:06+00:00

“ALMARJÃO” PROJECT

Subcontract details

Layher Blitz facade scaffolding

Client: UDRA Construtora Lda.

Location: Lisbon, Portugal
Execution Period: 8 months

Description:

Construção de urbanização habitacional composta por quatro lotes. Construction of a residential urbanisation comprising four plots. Approximately 7500m2 were erected with various accessories and types of scaffolding, including cantilevers, suspended scaffolding and interior back scaffolding. These scaffoldings varied in height up to a maximum of 34 metres. In total they represent 150 tonnes of “facade” scaffolding.

Various access stairs, mobile towers and lift boxes were also assembled on the multidirectional scaffolding. Systema Vertical also assembled four ALHER T2-CR freight elevators with a maximum load capacity of 1,300kg. Each unit has a mast height of 34 metres and nine automatic floor stops.

GALERY

CLICK ON THE IMAGES TO ENLARGE

SEE OTHER PROJECTS

AGEAS

2023-11-17T11:31:46+00:00

“AGEAS” PROJECT

Subcontract details

Layher Blitz Facade Scaffolding

ClientConstrutora San Jose 
Location: LPlot 1.10.02 – Parque das Nações, Ageas head office building
Execution Period:12 months

Description:

Construction of the Ageas head office building. Approximately 17,000 square metres of scaffolding were erected with various accessories and types of scaffolding, including cantilevers, suspended scaffolding and interior back scaffolding. These scaffoldings varied in height up to a maximum of 52 metres. In total they represent 340 tonnes of “facade” scaffolding. Various access stairs, mobile towers, platforms and lift boxes were also assembled on the multidirectional scaffolding.

GALERY

CLICK ON THE IMAGES TO ENLARGE

SEE OTHER PROJECTS

SMALL PALACE HENRIQUE MENDONÇA

2023-11-17T11:31:12+00:00

“SMALL PALACE HENRIQUE MENDONÇA” PROJECT

Subcontract details

Layher Allround multidirectional scaffolding

Client: Teixeira Duarte

Location: Henrique Mendonça Palace – R. Marquês de Fronteira, 18 – Lisbon
Execution Period: 9 months

Description:
Contract for remodelling and improving the Small Palace Henrique Mendonça. Approximately 4,000 square metres of scaffolding were erected with various accessories and types of scaffolding, including cantilevers, suspended scaffolding, towers for winches, access stairs and towers for passing material. These scaffoldings varied in height up to a maximum of 24 metres. In total they represent 90 tonnes of “multidirectional” scaffolding. A 600 m2 roof was also assembled.